President Ramchandra Paudel has praised the Nepali Army for its progress, professionalism and dedication in constructing the Kathmandu–Tarai/Madhes Fast Track, describing the breakthrough of the Mahadevtar Tunnel as a significant milestone in Nepal's national infrastructure development.
The 3,422-metre-long tunnel connecting Nijgadh towards Kathmandu achieved a breakthrough on Wednesday in the presence of President Paudel. The tunnel is part of the twin-tube Mahadevtar Tunnel being constructed in Bhimphedi and Bakaiya rural municipalities of Makwanpur district under the management of the Nepali Army.
Addressing the ceremony, President Paudel commended the Nepali Army for carrying out the strategically important national pride project despite geographical challenges, complex geological conditions and difficult construction environments.
He said the approximately 71-kilometre expressway would bring a significant transformation to Nepal's transportation system by reducing travel time and distance, fuel consumption and vehicle operating and maintenance costs. The project will also contribute to tourism promotion, trade and transit facilitation, regional economic development and stronger national unity.
President Paudel urged all stakeholders to maintain effective coordination and commitment to ensure the timely completion of the strategically important project.
According to the Nepali Army, with this breakthrough, excavation work has now been completed on six tunnels at three locations—Dhedre, Lendanda and Mahadevtar—out of the 14 tunnels being constructed at seven locations under the project. Meanwhile, the construction of the remaining eight tunnels at four locations is ongoing.
Brigadier General Bharat Lal Shrestha of the Nepali Army said the project had achieved 51 per cent overall physical progress. He noted that construction of the major structures was progressing, with substructure works completed in most locations. However, land acquisition issues in the Khokana–Dukuchhap section of Lalitpur remain a challenge. Efforts are under way to resolve the outstanding issues and advance the remaining contract management process.
Meanwhile, Minister for Infrastructure Development Sunil Lamsal has warned that contracts of underperforming construction companies would be terminated if they failed to meet their revised work schedules. Expressing dissatisfaction with contractors under packages 9A, 9B and 8B, he said repeated warnings and extensions had failed to deliver the expected results. He stressed that the government would not allow further unnecessary delays and expected substantial progress by Jeth. The minister also highlighted the project's contribution to developing skilled Nepali engineers and technical professionals, describing them as valuable national assets.
Wang Zhi, a representative of China State Construction Engineering Corporation Ltd., reaffirmed the company's commitment to completing the remaining construction works on time.
He thanked the Nepal government, concerned ministries and government agencies for their continued support and acknowledged the contributions of Nepali, Chinese and Korean engineers, technicians and workers.
Wang said the project had faced considerable challenges, including the COVID-19 pandemic and complex geological conditions in the Himalayan region. He pledged to accelerate the remaining works, particularly tunnel lining and structural construction, while maintaining strict quality control, safety standards and risk management.
The latest breakthrough marks an important step towards completing the Fast Track, which is expected to establish a direct and modern connection between the Kathmandu Valley and the Tarai/Madhes region.