Satv, Kathmandu, Nov. 27: The government has initiated the process of formulating a new energy mix policy to achieve its target of generating 30,000 megawatts (MW) of electricity within the next 10 years.
The Ministry of Energy, Water Resources and Irrigation is preparing a new framework to determine the proportion of electricity to be generated from different energy sources, including run-of-river, peaking run-of-river, reservoir-based, pumped-storage, solar and wind projects.
The new framework is expected to pave the way for the resumption of the Power Purchase Agreement (PPA) process, which has remained suspended for a prolonged period.
The ministry is preparing to determine the share of each energy source based on the country's future electricity demand and generation potential.
This will provide a basis for identifying the types and capacities of projects required to achieve the 30,000 MW generation target.
Currently, Nepal has an installed electricity generation capacity of around 4,200 MW, with a large proportion coming from run-of-river hydropower projects.
Such projects generate more electricity during the rainy season but produce less during winter, creating seasonal imbalances in electricity supply.
The ministry said the existing energy mix was designed based on a generation target of 15,000 MW. However, as the government has now set a target of 30,000 MW, a new framework has become necessary to meet long-term energy requirements.
281 hydropower projects await PPAs
The National Energy Crisis Reduction Policy and the Electricity Development Decade (2016–2026), introduced in 2016, had for the first time set targets for electricity generation from different sources.
It aimed to allocate 40 to 50 per cent of total generation to reservoir-based and pumped-storage projects and 15 to 20 per cent to peaking run-of-river projects.
Later, a framework based on the 15,000 MW generation target allocated 30 to 35 per cent to reservoir-based and pumped-storage projects, 25 to 30 per cent to run-of-river projects, 30 to 35 per cent to peaking run-of-river projects and 5 to 10 per cent to other alternative energy sources. Around 10 per cent was also proposed for solar energy.
After the Cabinet increased the share of run-of-river projects to 40 to 45 per cent in July 2022, the PPA process was adjusted accordingly.
Subsequently, the Board of Directors of the Nepal Electricity Authority (NEA) approved PPAs for run-of-river projects with a combined capacity of up to 1,500 MW.
The introduction of the 'take and pay' provision for run-of-river projects through the budget for the last fiscal year further affected the PPA process.
Since then, PPAs for both run-of-river and peaking run-of-river projects have remained suspended.
According to the NEA, it has so far signed PPAs with 404 run-of-river projects for a total capacity of 6,713.44 MW, 51 peaking run-of-river projects for 4,186.81 MW and one reservoir-based project for 140 MW.
Meanwhile, a total of 281 additional projects with a combined capacity of 16,425.77 MW are awaiting PPAs.
The absence of PPAs has affected financial arrangements required for project development.
As banks and financial institutions seek assurance of electricity sales, PPAs are considered a key basis for establishing the financial viability of hydropower projects. Therefore, the new energy mix is expected not only to facilitate the resumption of PPAs but also to encourage private sector investment, accelerate construction activities and create employment opportunities.
Energy mix to ensure year-round power supply, boost exports
According to the Ministry, another important aspect of the new energy mix is the inclusion of alternative energy sources.
The country's electricity generation plans have traditionally focused mainly on hydropower, although the share of solar energy has gradually increased. Electricity generation from wind energy, however, remains negligible.
Heavy dependence on hydropower has resulted in lower domestic generation during the winter, making electricity imports from India necessary to meet demand. To reduce this dependence, the government is preparing to incorporate solar, wind and other alternative energy sources into the national energy system.
The Ministry of Energy is conducting studies on the potential and generation capacity of these sources.
The new energy mix is expected to help maintain a balance in electricity supply during both the rainy and winter seasons. Reservoir-based and pumped-storage projects, in particular, can contribute to energy storage and ensure supply according to demand.
Similarly, the development of solar and wind energy can diversify generation sources and production patterns.
Once the new energy mix framework is finalised, the NEA will be able to move ahead with the PPA process based on the nature and requirements of individual projects.
This is expected to open the door for the development of projects with thousands of megawatts of combined capacity that have been waiting for investment opportunities.
Achieving the target of generating 30,000 MW of electricity will require the government to expand domestic consumption, transmission infrastructure and cross-border electricity trade alongside increasing generation capacity.
The increasing production will not be sufficient; strategies will also be needed to ensure electricity availability in line with seasonal demand and expand export markets, said the Ministry.
As the government explores greater electricity export opportunities to Bangladesh alongside India, a balanced energy mix could help increase the production of exportable electricity.